Alu-Schwinge K & J
Partlist:

 

 Please controll all delivered parts.

If any lost or damaged , contact us immedialety.

 

GFK Sidepices unpainted, left / right
Main support, 2 x m of 8 x 10, 2 x rubber nut M6, 2 x Imbus M 6 x 20, 2 x polyamide federation plate.
2 x sticking nuts M5, 2 x Imbus m of 5 x 20, 2 x Rubberdisc 6 mm, 2 x polyamide federation plate
1 x lower splashboard V2A -- 0.8 mm, 8 x rubber nut M4, 8, x Imbus M4 x 16
1 x top splashboard V2 A -- 0.8 mm, 4 x rubber nut M4, 4 x Imbus M4 x 16
2 x lateral air outlet frame V2A -- 0.8 mm, 8 X rubber nut M4, 4, x Imbus M4 x 16
-------------------------------------------------------------------------------------------------------------------------------
Caution!
The alliance plates serve as hole reinforcements and to the avoidance from disguising rips.
The alliance must be imported into the drilling.
---------------------------------------------------------------------------------------------------------------------------------
 
Please proceed exactly according to these packaging instructions.
You needfor a fault-free packaging is the fitting tool, technical understanding and a little sensitivity.
You need no blow tools crowbar and no acts of violence !!!

 

 

E.g. vehicle packaging for certain builds

on the main column, on-buck device or if not differently possible on the prop stand.
Opening out prop stands.

 

 

 

Dismantling of the left cooler disguising and the lamb ulnae in front at the cooler.

With water pump pliers you stick the Halteschelle the Wasser's lynx together and you turn these into this one
Position up like in the picture.

 

 

 

Shove the sticking nut about the hold latch of the frame behind, this on the left/on the right so shows the thread to the inside.
Put the main support together at the engine block into the available M8 threads in front.
 

 

 

 

Put the rubber nuts together into the GFK spoiler side at the underside, lateral air outlet, in front wedge.
If you put the lower splashboard together, they screw it in tight to approx. 70%.

 

Packaging of the lacquered parts at the ropest one with 2 persons!
Main support you hold the disguising to the vehicle and you fit the M6 screw with polyamide federation plate, mittg ()
Tighten the screw to approx. 70%.

 

Fit the upper cooler screw, tighten these too approx. 70%. 

 

You put the Gummischeibe Monitieren between GFK and sticking nut you the fastening screw behind,
you put the alliance nut into the existing drilling and you screw in tight the whole with approx. 70%
Put the panel together after the same scheme as the left on the right.
You pay attention that the lower metal aussen or you place to below.

 

If you fit the front Sprizblech (wedge) as well as all 4 screws at the lower metal, you tighten everything to approx. 70%.
Fit the front lower hold screw on the left and they tighten these too approx. 70% on the right.
 
 
 
 
13.
You check whether all parts are placed correctly to your satisfaction.
 
14.
Tighten the screws in the following round dance consequence now.
 
14/1. all 4 screws at the disguising wedge in front
14/2. all 8 screws at the sub-ground metal
14/3. respectively the screw at the main support on the left /rechts
14/5. Respectively the upper cooler screw
14/6. respectively the lower cooler screw
14/7. If you check the movability of the main column, at least an opening measure of 3 mm must be available on both sides, at firmly dressed screw.
You tighten the back screw if the movebility of the main column is given.

 

15. You are now (hopefully) happy owner of a high-quality Schwabenmax component, you handle carefully and carefully that   so you have long fun and joy it.
      
 
 
How do no annoying wish police controls and always a returning home healthily a rope journey, a lot of fun and joy, always?
 
Your Schwabenmax team